The largest BOT expressway project in northern Vietnam.
The biggest BOT expressway in the North with 2 sections of new construction and an overlay of existing national road No.1A. The project aims to enhance the transport of intensive numbers of heavy cargo truck fleet to export and import through the busiest border gate shared with China. ADCo supplied 12,000 MT of products, including all bituminous binder/emulsion (60/70 bitumen, PMB, and CRS1P and Novabond) with high-quality control and tight supply schedule under BOT company progress.
Product : RapidBond® (CRS-1P) RapidBond® Ultra (Novabond®) AC 60/70
Year : 2016-2017
Location : Bac Giang - Lang Son
Owner : Government
Consultant : A to Z, Viet Nhat Consultant
Contractor : Bac Phuong, LICOGI16, Hoa Hiep, Hop Tien, Hoàng Long, Ha Giang Cons. Co.
Scope of Work : 65km highway standard with 4 lanes and upgrade of 75km of NH1 with 2 lanes.